To supply and install replacement HV transformer 11kv to 415v as a direct replacement for transformer 3. These works to be carried at agreed time and within approved timescales. 1. Source and deliver to site 800kva eco transformer. 2. Isolate the existing Transformer and certify as safe to work. 3. With phasing marked remove the HV and LV cables, protect whilst transformer is being replaced. 4. Remove all earthing . 5. Remove Transformer 3 from the substation. 6. install a new ECO TIER 800kVA transformer or equivalent wound with compatible vectors to be compatible for parallel connection to Transformer No4 if required. 7. Replace the HV and LV cables, Replace all earthing, Test and commission with 4hr soak test.